1.
In its recent meeting the IASV
board had detailed discussion about prioritization of the
construction projects. The following projects were approved for the next three
years unanimously (the projects appears in time chronology):
a.
Construction the driveway starting from the
mailbox to the end of the parking lot near septic tank. This will serve as one
way entrance. Paved parking lot will be the one exit. One way exit on the
minaret side will be closed.
b.
Grading of the area behind the mosque up the
septic tank.
c.
Paving the parking lot adjacent to the currently
paved lot all the way to the trash dumpsters and to the kitchen area. This will
also create several new parking spaces. The money for most of this project
already has been budgeted; the rest will be solicited from the community. This
project is expected to be started in early spring and completed by the summer.
d.
The next phase will be construction of minaret
and dome, which is badly needed to strengthen the structure of the current
building. Funds will be solicited from the community and project is expected to
begin early next year.
e.
The last phase of the project will be
construction of the annex hall on the designated space east side (highway side)
of the building. Major fundraising drive will have to be conducted.
f.
These projects will be posted on the website.
Maps and drawings will also be posted in the lobby.
g.
Afridi will introduce the projects after the
Friday prayers on January 13 and subsequent Fridays if needed.
|
Capital Improvements |
|||||
|
Year One |
|||||
|
Site Preparation |
$25,000.00 |
||||
|
Parking, Ingress and |
|||||
|
Egress |
|||||
|
Engineering |
01-Mar |
||||
|
Project Begin |
01-Apr |
||||
|
Project Completion |
30-Jun |
||||
|
Minerate &
Dome |
$125,000.00 |
||||
|
Engineering |
01-Jun |
||||
|
Project Begin |
01-Jul |
||||
|
Project Completion |
15-Nov |
||||
|
Year Two - Four |
|||||
|
Prayer Hall Addition |
$400,000.00 |
||||